Design Process
Vashon Island Arts followed a defined process for the design of the Arts Center. The key was to involve as many Island groups as possible and to offer public opportunities for comment. To see when these steps occur, see the Project Calendar page.
Vashon Allied Arts Design Process
Step #1 – Select Architect
- Choose Design Firm
- Choose Consultants
Step #2 – Feasibility
- Define Preliminary Scope of Work
- Code Analysis
- Cost Estimating
Step #3 - Community Input
- Meet with Artists and Arts Groups
- Meet with Neighbors
- Meet with Community
- Revise Scope of Work
Step #4 – Schematic Design
- 15-20% Completed Building Drawings
- 15-20% Completed Site Drawings
- Meetings with Jurisdictions
- Meet with the Community
- Cost Estimates
Step #5 – Design Development
- 40-50% Completed Building Drawings
- 40-50% Completed Site Drawings
- Meetings with Jurisdictions
- Cost Estimates
Step #6 – Construction Drawings
- 100% Completed Building Drawings
- 100% Completed Site Drawings
- Permitting
- Cost Estimates
No comments yet